Demolition of (2) existing precast and cast-in-place bridges on I-294 over Grand Ave. and UPRR. Scope of work included a structural engineered approved demolition plan, demolition of the single span Grand Ave. bridge & the 3-span UPRR bridge over (2) active train tracks, demolition of the concrete support piers and abutments, and processing all concrete down to remove reinforcing steel. This work is being completed in (4) phases including day and night shift work, all while I294 stays in operation over the span of 2.5 years.
- ECC Demolition utilized a 550-ton crane to pick the concrete girders.
- Nightshift work had to be utilized for a complete closure of Grand Ave while picking the concrete girders.
- Working around constant train traffic at UPRR proved to be challenging with constant work stoppages.