Carson’s – Matteson
Complete demolition of 162,000sf 2-story Carson Pirie Scott. This Carsons was the last remaining portion of the former Lincoln Mall, a large retail shopping mall, consisting of approximately 750,000 square feet of space that was developed in the early 1970s. ECC Demolition completed all the asbestos abatement & demolition at Lincoln Mall over the previous several years. Scope of work included asbestos abatement; complete demolition of structure, including deep foundations for earth retention; onsite crushing of brick, block, and concrete; backfill of deep earth retaining foundation walls for safety, and stabilization of demolition area.
- ECC Demolition worked with Fire and Police departments so that they could utilize the existing building prior to demolition to get invaluable real-life training that they normally do not have the opportunity to experience.
- Deep excavation, clean out and grading of the storm water retention pond so that the volume was corrected, and the pumps could be replaced/repaired.
- ECC Demolition also performed in-house asbestos inspection, sampling, and laboratory analysis to determine asbestos was not present in the building prior to demolition.