333 Lake Street, Bloomingdale
Complete demolition of an 85,000 sf 3-story commercial office structure with a basement parking garage. Scope of work included complete demolition of structure including deep foundations for basement garage, backfill of basement, and stabilization of demolition area.
- ECC Demolition also performed, in-house, the asbestos inspection, sampling, and laboratory analysis to determine asbestos was not present in the building prior to demolition.
- We were required to stay off the existing pavement. ECC Demolition utilized its High Reach excavator to complete the demolition within the footprint of the structure.
- ECC Demolition also had to remove the roof ballast before starting the structural demo to avoid contaminating the concrete so that the concrete could be sent to a recycling facility.
- Spring Creek Reservoir Forest Preserve and bike path were directly next to the project, which made dust suppression a critical part of the project.