References
Asbestos Abatement and Total Demolition Castle Construction
Tolentine Center
20300 Governors Highway
Mike Bergin / 708.339.2600
Building was the former living quarters and gymnasium of The Augustinian Order, measuring approximately 34,836 square feet. We performed the removal of asbestos containing
floor tile and mastic, and transite siding, under NESHAP regulations, prior to complete demolition of the two story building in preparation for new development.


 

Asbestos Abatement and Total Demolition DeJames Builders
325 Whitewater John Maffia / 847.488.9801
Asbestos abatement of floor tile and mastic throughout building and total demolition of a one story, 10,000 sq. ft. former church.


 

Asbestos Abatement and Total Demolition Adelman Brothers
2783 N. Clybourn Avenue Skyler / 773.406.0255
Complete demolition of one story frame office and warehouse structure, a (former Century Lumber) approximately 6750 sq. ft.,
after removing asbestos floor tile from front lobby floor.


 

Asbestos Abatement and Total Demolition Steinmarch Development
2711 W. 183rd St. John Mott / 708.206.3580
Three story, approximately 41,000 sq. ft. of retail (former Walgreen’s) and office building, required asbestos abatement of floor tile and mastic,
and pipe insulation, prior to the total demolition of building.


 

Asbestos Abatement and Total Demolition V3 Companies of Illinois
Lincoln Mall Mike Famiglietti / 630.724.9200
Removal of known asbestos containing material (acm) located throughout selective stores in the Mall, prior to the total demolition of a Montgomery Ward’s, Montgomery Wards
Tire and Battery, and JC Penny’s. During demolition additional acm was found. This required us to stop the demolition, contain the material from being air born by wetting,
revise notifications to notify the appropriate agencies, bag and label the material, and dispose of bags at a licensed facility. Upon completion of the abatement we resumed
the demolition.


 

Asbestos Abatement and Total Demolition Walmart Stores Inc.
Drury Lane Dinner Threatre
& Ward’s Auto Center
Todd Lewis &
Zach Fredman /
630.916.1200
In preparation for the construction of a new Walmart, the referenced job included the demolition of a two story dinner theatre, a separate chapel, and an auto service center. Our
standard procedure began with securing all permits and notifications. We than coordinated the removal of all utilities, with the respective utility companies; while maintaining all
existing utilities to the surrounding businesses.Prior to demolition ECC removed and disposed of all asbestos containing materials existing on the site (floor tile, thermal insulation, and transite paneling), in accordance
with all applicable federal, state and local laws.

The demolition was performed by operators using excavators attached with grapples, taking the building apart, piece by piece, and sorting the material into piles, for recycling.

The demolition included all mechanical, electrical, plumbing, roofing, fire protection materials, wall partitions, structural and miscellaneous steel, concrete pads, light poles,
light pole bases, blocks, and bollards.


 

Asbestos Abatement and Total Demolition Franciscan Sisters of Chicago
Our Lady Victory Convent Ron Maine / 708.927.3122
Asbestos abatement and total demolition of multi-story masonry “mother” house. Prior to demolition, ECC removed asbestos containing pipe insulation, floor tile,
and mastic; and removed for recycling florescent bulbs, ballasts and mercury switches.


 

Asbestos Abatement, Total Demolition and Site Restoration Downers Grove Park District
Washington Center Gene Cromwell /
630.963.1304
Asbestos containing floor tile and mastic was removed and disposed of prior to the complete demolition of a former two-story masonry structure known as Washington School, and two
single family frame structures in preparation for a new park on the site. Environmental Cleansing Corporation acted as excavating and general contractor in the construction of the
new detention pond, retaining walls and final seeding and restoration of the site now known as Washington Center.


 

Asbestos Abatement and Demolition Franciscan Sisters of Chicago
Madonna High School Ron Maine / 708.927.3122
Asbestos containing floor tile and mastic was removed and disposed of prior to the complete demolition of a former two-story masonry structure known as Washington School, and two
single family frame structures in preparation for a new park on the site. Environmental Cleansing Corporation acted as excavating and general contractor in the construction of the
new detention pond, retaining walls and final seeding and restoration of the site now known as Washington Center.


 

Demolition Mid-America Investment &amp Development
Cook School, Oak Lawn Mike Nortman /
630.954.7372
After Preservationists failed to find funding to renovate the Historic Cook School, the building was slated for demolition.
E.C.C. performed the tear down, carefully salvaging all decorative stone to be incorporated in a future memorial.


 

Demolition School City of Hammond
Washington Irving Elementary School Tom Eckterling /
219.661.8380
Contract included complete demolition of existing building, parking lots, side walks, curbs, and playground equipment.


 

Asbestos Abatement, Demolition and Environmental Remediation J. Sterling Morton High School Dist. 201
Anderson Elevator and Economail Dave Paukner /
708.747.3600
This project consists of the demolition of two industrial/manufacturing buildings comprising 205,000 square feet. Small amounts of asbestos containing materials including transite
siding, floor/tile/mastic and thermal systems insulation were removed. The entire built up roof system containing asbestos is being removed as demolition debris as allowed by NESHAP
regulations, pertaining to demolition. Drums of regulated materials were collected from throughout the buildings and staged for collection and disposal at licensed waste treatment
facilities. Over packing of some items was required. All fluorescent bulbs and PCB ballasts were also removed and sent for recycling.Underground storage tank removal will be performed at a later date for two (2), 10,000 gallon heating oil tanks. The building housed a manufacturing business, utilizing oils in the
process. Aboveground tanks, pressure chambers and process piping were pumped, purged, vacuumed and cleansed prior to their dismantlement.


 

Asbestos Abatement and Total Demolition Walsh Construction Company
Former K-Mart Vlad Stevanovick
Asbestos abatement and total demolition of former K-Mart and Payless Shoe store in preparation for construction of a new Target store. All fluorescent bulbs, ballasts and mercury
switches were removed and recycled.


 

Asbestos Abatement and Total Demolition United States Department of Energy
Argonne Buildings 200, 198, 201 and 230 Ron Ghilardi / 630.252.7031
Numerous projects were performed at Argonne National Laboratory, operated by the University of Chicago, on behalf of the Department of Energy. We have performed work including selective
mechanical demolition, cooling tower demolition, lead abatement, asbestos abatement, aboveground utility removal, underground utility removal, process equipment and experiment dismantling,
total demolition and site grading. All work performed at Argonne National Laboratory requires the strictest adherence to safety regulations and documentation. All work is inspected daily
by Argonne safety personnel and construction field representatives.


 

Asbestos Abatement
and Interior Demolition
Draper and Kramer Incorporated
Palmolive Building, 919 N. Michigan Ave. Carl Peterson /
312.795.2329
Interior abatement of lead and asbestos followed by total interior demolition of multiple floors. Obtain all necessary permits. Legally transport and dispose of all
asbestos material and demolition debris.


 

Asbestos Abatement and Total Demolition Home Depot USA Midwest Division
Home Depot /
Oak Lawn, Illinois
Rick Lally /
847.870.5153
Asbestos abatement, special waste removal and total demolition of multiple existing structures totaling one hundred, forty-seven thousand square feet.
Abatement included floor tile, mastic and roof flashing materials. All fluorescent bulbs, ballasts and mercury switches were removed and recycled.E.C.C. was assigned a stringent time line to follow and delivered a fully completed site eleven days ahead of schedule, to facilitate the start of a new “Home Depot”.


 

Asbestos Abatement and Total Demolition Home Depot USA Midwest Division
Home Depot /
Oak Lawn, Illinois
Rick Lally /
847.870.5153
Asbestos abatement, special waste removal and total demolition of multiple existing structures totaling one hundred, forty-seven thousand square feet.
Abatement included floor tile, mastic and roof flashing materials. All fluorescent bulbs, ballasts and mercury switches were removed and recycled.E.C.C. was assigned a stringent time line to follow and delivered a fully completed site eleven days ahead of schedule, to facilitate the start of a new “Home Depot”.


 

Asbestos Abatement, Demolition and Concrete Crushing Tri-Land Properties
Century Mall /
Merriville, Indiana
Phil Leach
Removal and legal disposal of all asbestos containing material prior to demolition. Demolish one story mall, consisting of eighty-four stores, leaving the two anchor tenant stores intact.Maintained two electrical services that feed parking lot lights and adjacent buildings. Transported and assembled mobile concrete crusher to project site and crushed twenty thousand
tons of concrete. Backfilled site, and transported balance of finished material off site.


 

Asbestos Abatement and Total Demolition Evergreen Park & Associates
Evergreen Plaza Theaters Dale Reska / 708.423.5352
Remove asbestos material and total demolition of thirty three thousand square foot structure. Demolished all connecting bridges to structure. Demolish building to one foot
below grade, including islands around all support columns. Barricades were provided for the protection of pedestrians and motor vehicle traffic. Transport and legally disposed
of all asbestos and demolition debris.


 

Asbestos Abatement and Demolition MGA Management Services
Merchantile National Bank /
550 West Jackson (Phase One)
Dan Novak / 312.280.9524
In the first part of this project, ECC performed approximately 16,000 square feet of selective interior demolition and related services, including the removal of two ceilings,
interior walls, column wraps and a 24′ x 18′, concrete reinforced bank vault.The second part of this project was the asbestos abatement. This involved the gross removal of approximately 57,000 square feet of floor tile and mastic, thermal pipe and elbow
insulation, sprayed on structural fireproofing and the transportation and legal disposal of all asbestos material.

As with all of our abatement projects, upon its completion the owner receives a bound “Documentation Package” as their permanent record or our activities on the job.

This project required the work be done from 5:30 pm to 2:00 am, in order to avoid disrupting the daily business activities.


 

Selective Interior Demolition and Asbestos Abatement MGA Management Services
550 West Jackson (Phase 2) Dan Novak / 312.280.9524
This project involves the interior demolition of 100,000 square feet of building, starting at four floors above occupied tenant space. We were required to remove all construction materials
down to the shell of the building.Environmental Cleansing Corporation (ECC) also is providing the removal of 100,000 square feet of sprayed on fire proof asbestos containing material; and 3,000 linear feet of pipe
insulation. Two crews performed the work.


 

Demolition Capitol Development Board
Pullman Historic Site Jim Jakomis / 708.754.0252
Pullman’s Palace Car Factory, a historical site in the state of Illinois was once the working centerpiece of a company town built in the 1880’s by railcar magnate George M. Pullman,
On December 1, 1998 much of what the factory was nearly destroyed by a fire.Environmental Cleansing Corporation (ECC) has been instrumental in preparing this site for preservation. Our services include the asbestos abatement and demolition of the south factory;
selective demolition of the administration building, and the North pavilion, for a total of over 100,000 square feet of demolition.


 

Demolition Hiffman, Shafer and Associates
Orland Park Place Mall Tim Blum / 312.332.s3555
The demolition plan of this job had several phases. The first required Environmental Cleansing Corporation (ECC) to demolish thirty percent (30%), (over 200,000 square feet) of an
existing two story mall building in its entirety; phase two was to provide selective demolition and interior gutting (400000 square feet) of remaining area of mall and former
Wieboldt’s building; phase three was the excavation for new building foundations and footings and mass excavation of parking lot totaling 100,000 cubic yards of material.Environmental Cleansing Corporation (ECC) on its’ own behalf, notifies J.U.L.I.E. prior to any excavation or below grade demolition to allow utility marking. The dig number from
J.U.L.I.E. is recorded and becomes a permanent part of the demolition files.

All glass was removed to avoid the hazards from fragmentation, as they exist at the job site. Except where necessary, (non-identified), demolition began at the top of the structure and
proceeded downward i.e., roof, top of exterior walls, second floor, lower walls, first floor foundation. Each level of demolition was completed prior to progressing to the next lower
level. Debris was dropped through holes in the floor and walls in areas protected by a minimum six (6) foot setback and barricaded on all sides of exposure to a height of 42 inches.
Warning signs of falling materials were posted at each level. Steel construction was dismantled by column length and tier-by-tier.